A. Can do a piece of work in 7 days of 9 hours each, and b can do it in 6 days of 7 hours each. How long will they take to do it, working together 8 2/5 hours a day?

Answers

Answered by thivyathivi1995
1

Answer:

3 days

Step-by-step explanation:

A can complete a work in (7×9)=63 hours

B can complete work in (6×7)=42 hours

A's 1 hours work =1/63

B's 1 hours work = 1/42

(A+B)'s 1 hours work= (1/63 + 1/42)

= 5/126

both will finish the work in 126/5 hours

number of days of 8 2/5 hours each

=126/5 ÷ 8 2/5

=126/5 ÷ 42/5

= 126/5 × 5/42

= 3 days