A can do a piece of work in 70 days and B is 40% more efficient than A. The numberof days taken by B to do the same work will be?
Answers
Answered by
0
Answer:s
Step-by-step explanation:
40 percent of A = 40÷100X 70
=28 days
Hence, B will take 28 days as opposed to A
Hope this helps!!