Math, asked by srividhyaviiif20, 6 months ago

A can do a piece of work in 8 days and B can do it in 4 days. Both of them working together will finish it in

Answers

Answered by Ayush733092
2

Answer:

64hours

Step-by-step explanation:

A + B speed = 1+2

A + B speed = 3times

Both of them working together will finish it in = 8/3

Days convert into hours

= 8*24

= 192hours

= 192/3

= 64hours