a can do a piece of work in 8 days which b along can do in 10 days . in how many days both working together can do it
Answers
Answered by
0
Answer:
ECB bgghjldhhn vkgb# kvv
Answered by
2
METHOD 1
A alone can do the work in 8 days
So In One day A can do 1/8th work
B alone can do the same work in 10 days
So In One day B can do 1/10th work
One day work of A and B when working together is
1/8+1/10=9/40
So number of days they take to complete the entire work 40/9 days.
METHOD 2 LCM APPROACH
A = 8days
B = 10days
LCM(8,10)=40
This is the total work i.e = 40 units
So A per day work =40/8=5units
B per day work =40/10=4units
Per day work when A and B together works = (5+4)units=9units
So A and B together take 40/9 days to complete the entire work.