A can do a piece of work in 80 days and B can do the same work in 100 days. They work together for 20 days and B leaves. How many days will A take to complete the work?
Answers
Answered by
0
Answer:
60 days long
Step-by-step explanation:
A will take 60 more days to complete the work because A has already worked for 20 days