A can do a piece of work in 80 days and B in 100 days. They worked together for 20 days
then B goes away. In how many days will A finish the remaining work
Answers
Answered by
2
Hello mate here is your answer
It's given that
A can do a piece of work in = 80 days
A's 1 day work is = 1/80
B can do a piece of work in = 100 days
B's 1 day work is 1/100
If A and B work together they take time :-
( A+B )'s 1 day work is = (1/80) + (1/100)
= { ( 50+4 ) / 400 }
= 54/ 400
A and B work together for 20 days
Now,
(A+B ) 's 1 day work = 54/400
(A+B) 's 20 day work is = 20×54/400
= 54/20
Remaining work is = [ 1-54/200 ]
= [( 200 - 54) /200 ]
= 146/200
Now, after it B left the work
Alone A's work in 1 day is = 1/80
and the remaining work is 146/200
Now,
How many days taken by A to finish the work =
(146/200)×80
= 146/20 × 8
146/5 ×2
292/5
58 ⅖ days Answer