a can do a piece of work in 80 days he worked it for 10 days and then B alone finish the work in 42 days The two togethers could complete the work in how many days
Answers
Answered by
2
do part of park in 1 day=1/80
Work done by ajay in 10 days=10/80
=1/8
Remaining work=1-1/8
=7/8
B complete in 42 days=7/8part of work
B can complete in1day=1/48part of work
So B alone can complete it in 48 days
Work done by both in 1 day
=1/80+1/48
=(3+5)/240
=1/30
So they can finish the work together in 30days
Answered by
7
Step-by-step explanation:
Total Work = 80 units
A --> 80 days = 1 unit / day
In 10 days A has completed 10 units
Remaining work = 70 units
B finishes it in 42 days
Rate of work if B = 70 / 42 = 5/3 unit / day
A + B = 1 + 5/3 = 8/3
Time taken if both A and B will work together = 80/8/3
= 30 days
Hope it will help you .