Math, asked by romoyo10, 1 year ago

A can do a piece of work in 80 days. He works at it for 10 days & then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work? 

A.    23 days


B.    25 days


C.    30 days


D.    33 days

Answers

Answered by Anonymous
13

Answer : C.

Work done by A in 10 days=10/80=1/8

Remaining work=(1-(1/8))=7/8

Now, work will be done by B in 42 days.

Whole work will be done by B in (42*8/7)=48 days

Therefore, A's one day's work=1/80

B’s one day's work=1/48

(A+B)'s one day's work=1/80+1/48=8/240=1/30

Hence, both will finish the work in 30 days.