A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes
the work in 42 days. The two together could have completed the work in
Answers
Answered by
10
Answer:
30 days
Step-by-step explanation:
In 80 days A can do the work, in 1 day he does 1/80 part of the work.
He works for 10 days. In 10 days he does 10x1/80 part=1/8 part of the work.
Remaining part of work left=1-1/8=7/8 part
In 42 days B does 7/8 part of the work. In 1 day he does (1/42)x(7/8)=1/48 part
A and B in 1 day do=1/80+1/48=1/30 part.
They would finish the work in 30 days.
Answered by
0
Let total work =1
A's one day work =1/80
Let B take x days to finish work alone,
then B's one day work =1/x
Total Work done by A= (days worked by A)*(A's one day work)=10*(1/80)=1/8
Work left =1−1/8=7/8
Now B completes the left work in 42 days,
(B's one day work)×42=(7/8)
(1/x)×42=7/8
7x=8×42
x=48
(A+B)'s one day work =(1/80)+(1/48)
Total time needed by (A+B) to complete
Similar questions