Math, asked by sumit87888027, 10 months ago

A can do a piece of work in 80 days.He works it's for 10 days then B alone finish the remaining work in 42 days. then A and B together could complete the work in ....

Answers

Answered by kashu5263
5

Answer:

Ashok's 10 day's work = 10/80 = 1/8

Remaining work = (1 - 1/8) = 7/8

7/8 work is done by Bhuwnesh is 42 days

therefore whole work will be done by B in (42* 8/7) = 48 days

Therefore (Ashok + Bhuwnesh)'s 1 day's work = 1/80 + 1/48 = 1/30

Hence both together can finish the work in 30 days

understand it through unitary method

Answered by RAGEToufik
6

Step-by-step explanation:

done the sum please check if it is right or wrong