A can do a piece of work in 9 days and B can do it in 6 days. With the help of C, they finish the work in 3 days. Then in how many days C alone can do the work?
answer plzz
Answers
Answered by
1
Answer:
18 days
Step-by-step explanation:
A = 9days = 1/9
B = 6days = 1/6
A+B+C = 1/3
(1/9)+(1/6)+(1/C) = 1/3
1/C = (1/3) - (1/9) - (1/6)
1/C = 1/18
C alone do a work in 18 days