Math, asked by krishnay0003, 1 month ago

A can do a piece of work in 9 days and B in 18 days. They b begin together but A goes away 3 days before the work is finished. How long will the work last.​

Answers

Answered by KamilSinghThakur
2

Answer:

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1ie (3×X + 3)/18 = 1

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1ie (3×X + 3)/18 = 1ie 3×(X+1)/18 = 1

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1ie (3×X + 3)/18 = 1ie 3×(X+1)/18 = 1ie (X+1)/6=1

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1ie (3×X + 3)/18 = 1ie 3×(X+1)/18 = 1ie (X+1)/6=1ie X+1=6

A can finish work in 9 days so A's work capacity per day is 1/9 part of work per day.Similarly B's work capacity is 1/18 part of work per day.Let us assume, the A and B worked together for X days and then A left the work, then remaining work was completed by B in 3 days (as per the problem statement), so B worked for X+3 days.So A's total work: X×1/9 and B's work is (X+3)×1/18So Eqn is X/9 + (X+3)/18 = 1ie {2×X + (X+3)}/18 = 1ie (3×X + 3)/18 = 1ie 3×(X+1)/18 = 1ie (X+1)/6=1ie X+1=6ie X = 5 so A and B worked together for 5 days and work got completed by B after 3 days, so total time taken to complete the work is 8 days.

I hope this may help you

May God bless you. stay safe

Have a great day

Similar questions