A can do a piece of work in 9 days. B is 50% more efficient than A. the no. of days it takes B to do the same piece of work is.
Answers
Answered by
1
a - 9 days
b - 6 days
lcm 18 divided by efficiency 3 gives 6 answer
b - 6 days
lcm 18 divided by efficiency 3 gives 6 answer