A can do a piece of work in ‘X’ days and B can do the same work in (X+16) days. If both working together can do it in 15 days, Calculate X.
Answers
Answered by
1
Answer:
24 days
Step-by-step explanation:
Answered by
2
Answer:
the value of x is 24 days