Math, asked by ngb1, 1 year ago

A can do a piece ofwork in 14 days while B can do it in 21 days. They begin together. But 3 days before thecompletion of work A leaves off.Find thetotal number of days taken to complete the work

Answers

Answered by umesh47
1
together complete the h w in 30 days

ngb1: Please send complete workout