A can do a price of work in 12 days and B alone can do it in 16days. they worked together on it for3 days and then A left. how long did B take to finish the remaining work.
step by step
chapter is time and work
Answers
Answered by
1
Answer:
15 days
Step-by-step explanation:
Given,
A can do a price of work in 12 days and B alone can do it in 16 days.
A=1/12 days
B=1/16 days
LCM of 12,16 is 48
they worked together on it for 3 days and then A left.
3/48=1/16 worked together
remaining work 1-1/16=15/16
15/16 work can be done by B in 16 days
15/16*16=15 days