Math, asked by Aahan007, 1 month ago

A’ can do a work 18 days and ‘B’ can do the same work in 12 days.

i. How much work will A finish if he works for 6 days?

ii. How much time will B need to finish the remaining work?

iii. Time taken by B to complete the remaining work.​

Answers

Answered by ojasva36
0

Answer:

i) 1/3 of the work

ii) 8 days

iii) 8 days

Step-by-step explanation:

A take 18 days to finish one work

therefore 6/18 = 1/3

Work A does in 6 days = 1/3 of the total work

A does 1/3 of work

therefore 2/3 work is remaining

2/3 *12 = 8

B will take 8 days to complete remaining work

Last one is same as second one