Math, asked by jaishabhola1, 1 month ago

A can do a work in 10 days and B can do it in 15 days. They worked together for 4 days and then A left the work . In

how many days can B finish the remaining work?

ANSWER CORRECTLY
(EXPLANATION)​

Answers

Answered by fa2viclass
0

Step-by-step explanation:

  1. work done =1/A+1/B
  2. 1/10+1/15=3/30+2/30=5/30=1/6
  3. now we should reciprocal 1/6=6
  4. A ,B combine to do the work =6 days
  5. already A done the 4days work then the remaining work B should done by 4-6=2days
  6. A=4days,B=2days
Answered by Propar1111
1

Answer:

5 days

Step-by-step explanation:

Work to be done = x

work x done by A in days = 10

work done by A in one day is 1/10 = 3/30

work x done by B in days = 15

work done by B in one day is 1/15 = 2/30

LCM of 10 and 15 = 30

Work done by A in 4 days = \frac{3*4}{30} = \frac{12}{30}

Work done by B in 4 days = \frac{2*4}{30} = \frac{8}{30}

Total work done in 4 days = \frac{12}{30}+\frac{8}{30}  =  \frac{20}{30}

Work left = \frac{10}{30}

Time taken by B to complete the task is \frac{10/2}{30/30} =5

Similar questions