A can do a work in 10 days and B can do it in 15 days. They worked together for 4 days and then A left the work . In
how many days can B finish the remaining work?
ANSWER CORRECTLY
(EXPLANATION)
Answers
Answered by
0
Step-by-step explanation:
- work done =1/A+1/B
- 1/10+1/15=3/30+2/30=5/30=1/6
- now we should reciprocal 1/6=6
- A ,B combine to do the work =6 days
- already A done the 4days work then the remaining work B should done by 4-6=2days
- A=4days,B=2days
Answered by
1
Answer:
5 days
Step-by-step explanation:
Work to be done = x
work x done by A in days = 10
work done by A in one day is 1/10 = 3/30
work x done by B in days = 15
work done by B in one day is 1/15 = 2/30
LCM of 10 and 15 = 30
Work done by A in 4 days = =
Work done by B in 4 days = =
Total work done in 4 days =
Work left =
Time taken by B to complete the task is
Similar questions