'A' can do a work in 10days and 'B' can do the same work in 16days . with the help of C they do the work in 4 days only. in how many days 'C can do the work alone ?
Answers
Answered by
13
Step-by-step explanation:
A can do the work in = 10 days
work done by A in one day = 1/10
B can do the work in = 16 days
work done by B in one day = 1/16
work done by A and B in one day (A+B) = 1/10+1/16
= 8+5/80. => 13/80
A, B,C can do the work in = 4 days
work done by A, B, C in one day = 1/4
so, the work done by C in one day =( A+B+C)-(A+B)
=> 1/4 - 13/80. => (20-13)/80.
=> 7/80
so, C can do the work alone in = 80/7
=> 11 3/7 days.
I hope it will help you sister.