A can do a work in 10days which is done by B in 15 days and by C in 20 days.They work together for 4days and B leaves.In how many days C and A together will finish the remaining work
Answers
Answered by
0
do LCM with minus
and 1 piece of work
Answered by
0
A = 10days
B = 15days
C = 20days
total unit of work is 120 unit
for 1day,
A = 12 unit in 1 day
B = 8 unit in 1 day
C = 6 unit in 1day
so,
A+B+C = 12 + 8 + 6 = 26 unit in 1 day
so,
4 day = 26* 4 = 104 unit
remaining work = 120 - 104 = 16 unit
so
C + A = 6 + 12 = 1day
18 unit = 1day
1 unit = 1/18 days
16 unit = 16/18 = 8/9 days