Math, asked by arunkumararumugam98, 8 months ago

A can do a work in 12 days; B in 6 days and C in 3 days. A and B start
working together and after a day, C joins them. The total number of days
required to complete the work is​

Answers

Answered by laksh046
1

Answer:

4 days because c joins them after a day and he can do it in 3 days so 1+3=4

Answered by stefangonzalez246
0

The total number of days they need to work is 16/7.

Number of days A takes = 12 \ days

Number of days B takes = 6 \ days

Number of days C takes = 3 \ days

According to the question, A and B start working together and C starts a day later.

Let the total number of days all three take to complete the work =x \ days

So A and B will work for x days and C will work for (x-1) days.

So,

x(\frac{1}{12})+x(\frac{1}{6})+(x-1)\frac{1}{3}=1\\ \\ \implies  \frac{x}{12}+ \frac{x}{6}+ \frac{x}{3}=1+\frac{1}{3}  \\\\\implies \frac{x+2x+4x}{12}=\frac{4}{3}  \\\\\implies \frac{7x}{12}=\frac{4}{3}\\ \\ \implies \frac{7x}{4}=\frac{4}{1}\\ \\ \implies x=\frac{16}{7}

Hence the total number of days needed to complete the work together is \frac{16}{7}=2\frac{2}{7} days.

#SPJ2

Similar questions