a can do a work in 12 hours, while B can do it in 8 hours. with the help of C they can do it in 4 hours . how long will C take to complete the job​

Answers

Answered by swarupas45458
0

Answer:

24hours

Step-by-step explanation:

Attachments:
Answered by Anonymous
0

Answer:

24 hours.

Explanation:

Let total work done be 1.

Work done by A in 1 hour is 1/12th of the total work and that done by B would be 1/8th of the whole work. Therefore, total work done together by A and B :

1/12 + 1/8 = 20/96 = 5/24    of the work.

Work done along with C in one hour would be 1/4th of the work.

So, Work done by A+B+C = 1/4th of the work

5/24 + C = 1/4

C = 1/4-5/24 = 1/24

Therefore, time taken by C to complete the work is 1 divided by 1/24 which gives 24 hours.