A can do a work in 14 days B can do in 21 days. They begin together but 3 days before the completion of the work A leaves off. The total number of the days to complete the work is:

Answers

Answered by tnwramit1
2
Make one correction in above image

A's one day work = 3
B's one day work=2
Last three day only b works
=2x3=6

Work left =42-6=36

A+b=5

Time=36/5=7 1/5

Total time =10 1/5 day


This is ur ans hope it will help you in case of any doubt comment below