A can do a work in 15 days and b in 20 days both work together for 5 days and then a left the work how long will b take to complete the remaining in work
Answers
Answered by
0
Answer:
vvjansgdv dhhebryrhbrudbrbfydgdbdgf
Answered by
0
B WILL TAKE 40/3 DAYS TO COMPLETE THE WORK