A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

Answers

Answered by pulkitarora28
2
8/15
1 day work of A=1/15
1 day work of B=1/20
Total work in a day=7/60
Work in 4 days=28/60
=7/15
Left work=8/15