Math, asked by sneha123468, 4 months ago

. A can do a work in 15 days and B in 20 days.
If they work on it together for 4 days. Then the
fraction of the work that is left is
first correct answer will be marked brainliest​

Attachments:

Answers

Answered by anirudhbhatia
1

Answer:

Take LCM of 15 and 20 as the total amount of work which is 60 units in this case.

A can do work in 15 days therefore amount of work done by A in 1 day is 60/15 = 4 units

B can do work in 15 days therefore amount of work done by A in 1 day is 60/20 = 3 units

Total amount of work done in 1 day =A work of 1 day+B's work of 1 day=4 units +3 units=7 units

Amount of work done in 4 days =4*7=28 units

Amount of Work Left = 60–28=32 units

Fraction of work left = Amount of work left/ Total Work = 32/60 = 8/15.

Hope This Helps You. Study Hard