A can do a work in 15 days. B in 25 days and C in 30 days. How long will they take to do the work if they work together?

Answers

Answered by hfhviyfd
1

Answer:

it will take

7 \frac{1}{7} days

Step-by-step explanation:

time taken by A=15days

work done by A in 1 day=1/15

time taken by B=25 days

work done by B in 1 day=1/25

time taken by C=30 days

work done by C in 1 day=1/30

work done in 1 day if they work together =

 \frac{1}{15}  +  \frac{1}{25}  +  \frac{1}{30}  =  \frac{10 + 6 + 5}{150}  =  \frac{21}{150}

so to find the work done when time is given we simply do

 \frac{time}{1}  =  \frac{1}{time}

in similar manner to find time

 \frac{1}{work}  =  \frac{work}{1}

so total work in 1 day=21/150

total time=

 \frac{150}{21}  = 7 \frac{3}{21}  = 7 \frac{1}{7} days