A can do a work in 15 days. B is 50% more efficient than A . Then find out how many days required to complete the work when both are working together
Answers
Answered by
0
Answer:
Because efficiency and time taken is inversely proportional to each other. Hence 15 days is 50% more than the time taken by B. B = 15*(100/150) = 10days