A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.
A) 4/9 B) 1/4 C) 1/5 D) 2/9
Answers
Answered by
1
Answer:
A can do a work in 15 days and B in 20 days. If they work together for 4 days then what is the fraction of work that is left?
Between working remotely and working securely, there’s Webex.
Let's tKe total work as LCM of 15 and 20,
Total work = 60 units
A finishes work in 15 days, therefore does 60/15 = 4 units in a day
B finishes work in 20 days, therefore does 60/20 = 3 units in a day
In a single day working together they finish = 4+3 = 7 units
Working together for 4 days, they will finish = 4*7 = 28 units
Part of work finished so far is = 28/total work = 28/60 = 7/15