A can do a work in 20 days. B can do it in 15 days. C can do it in 12 days. If they work together, how much time would it take to complete the work.
a)5
b)6
c)8 2/3
d) 20 2/5
Please help me : )
Answers
Answered by
0
Answer:
I don't really know but your answer could be 5 days. Yes.
Answered by
1
Answer:
(a) 5
Step-by-step explanation:
Formula:
1/x = 1/A + 1/B + 1/C
Solution:
1/x = 1/20 + 1/15 + 1/12
1/x = 1/5
x = 5