A can do a work in 20 days. B can do it in 30 days. if they work together how many days required to complete the work
Answers
Answered by
2
Answer:
A can do a work in 20 days
so Work done by A in 1 day=1/20
B can do a work in 30 days
so Work done by B in 1 day=1/30
Work done by (A+B) in 1 day = (1/20 + 1/30)=1/12
No. of days required to complete the work= 1/(1/12)=12 days.
Similar questions
Math,
3 hours ago
Math,
3 hours ago
Hindi,
3 hours ago
Social Sciences,
5 hours ago
English,
8 months ago