Answer:
A can do a work in 20 days
so Work done by A in 1 day=1/20
B can do a work in 30 days
so Work done by B in 1 day=1/30
Work done by (A+B) in 1 day = (1/20 + 1/30)=1/12
No. of days required to complete the work= 1/(1/12)=12 days.