A can do a work in 20 days while b can do it in 12 days. B worked at it for 9 days. A can finish the work in how many days?
Answers
Answered by
3
Answer:
Lets give the piece of a work a nice round number, 100
So the ‘piece of work’ takes 100 units to complete.
If A can do it in 20 days, they are doing 100/20 units of work per day
100/20 = 5.
B can do the 100 units in 12 days
100/12 = 8.33..
If B does 9 days worth of work, that will be 9 * 8.33… = 75 units.
We need to subtract 75 from the original 100 units of work to see how much work is left to do.
100 -75 = 25 units of work.
Given A does 5 units of work a day, we divide 25 by 5 to tell us how many days it will take to finish the remaining work
25/ 5 = 5
Thus it will take 5 days for A to finish the remaining work.
Answered by
6
A will finish it in 5 days
hritu1911:
I could have marked you as the brainliest but you just wrote the answer and did not explain it into steps. so sorry but thanks for writing to me and your answer was absolutely correct
Similar questions