A can do a work in 25 days B can do a work in 20 days the start the work together ,after 5 days A left. How many days will B take to complete the remaining work?​

Answers

Answered by anjalikhatkar1234
2

Answer 11 more may be............

Answered by RvChaudharY50
1

Answer:

25, 20 LCM = 100

efficiency = 4, 5

in first 5 days both do = 9*5 = 45 unit of work

Now, 55 unit of work left and A gone .

rest work do by B in = 55/5 = 11 days [ Ans.]

[ mark as brainlist]