A can do a work in 3 days less than B. A works it alone for 4 days and then B took over and
completes it. Altogether 14 days were needed to complete the work, how many days does each of them take to do the work alone?
Please answer correctly!!!!!!!!!!
Answers
Answered by
2
Let A completes in x days
then B in x+3 days.
Total work ( lcm of x and x+3 ) = x ( x+3)
Since efficiency ∞ 1/time
So , efficiency of A= x+3work / day
And efficiency of B= x work / day .
Efficiency * days = work
( x+3)*4+ x*10 = x( x+3)
x^2- 11x-12 = 0
x= 12
A alone take = 12 days ,B= 15 days
mark as brainlist answer
hope it will help you
Answered by
2
Answer:
Step-by-step explanation:
can finish work in x - 3 = 15 - 3 = 12. Hence, A and B can individually finish the work in 15,12 days respectively.
Similar questions