A can do a work in 36 days, B in
18 days and C in 12 days. Every
2nd day B and every 3rd day C,
helps A.Then in how many days
the work will be completed?
Answers
Answered by
1
Answer:
14 days
Step-by-step explanation:
Let to work Total Work = 36
One day work of A = = 1 unit/day
One day work of B = = 2 unit/day
One day work of C = = 3 unit/day
In 3 days cycle total work done is A, A + B, A + C = 1 + (1 + 2) + (1 + 3) = 8 unit/Cycle
∴ 32 units of the work completed in 4 cycle and reminder 4 units of works in next two days.
1 cycle = 3 days
∴ 4 cycle = 12 days
And remaining 4 unit work done in next two days. In days 13, A will work 1 unit and in day 14, A and B will work 3 units.
Total number the day required to complete the work in the given condition is 14 days
Answered by
0
Answer:
I can't understand this que plz clear it and resend........
Step-by-step explanation:
Similar questions
Math,
3 months ago
Hindi,
3 months ago
English,
8 months ago
Social Sciences,
11 months ago
Science,
11 months ago