a can do a work in 45 days he worked at it for 15 days and then B alone finish the remaining work in 24 days find the time taken to complete 80% of the work if they work together
Answers
The time taken to complete 80% of the work if A & B work together is 16 days.
Step-by-step explanation:
A alone can do a work in 45 days
So, work done by A in 15 days = =
∴ Remaining fraction of work that is done by B alone = 1 - = ← in 24 days
∴ The whole work will be done by B alone in = 24 × = 36 days
Now,
Work done by A in 1 day =
Work done by B in 1 day =
∴ Work done by A and B together in 1 day is given by,
=
=
=
=
If, 1 whole work is done by A and B together in 20 days
Then, 80% of the work will be done in = 20 * = 16 days
-------------------------------------------------------------------------------------
Also View:
A can do a piece of work in 80 days. He works at it for 10 days & then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work?
https://brainly.in/question/3605419
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work?
https://brainly.in/question/5332206
A can do a piece of work in 60 days.he works for 15 days and then b alone finishes the remaining work in 30 days. the two together can finish the work in?
https://brainly.in/question/5406689
Time taken to complete 80% of the work when A and B works together is 16 days
Step-by-step explanation:
Given as :
A can do a work in 45 days
A's 1 day work =
So, work done by A in 15 days = 15 ×
=
Remaining work = 1 -
i.e Remaining work = =
Now, B alone finishes the remaining work in 24 days
So, Remaining Work done by B in 24 days = 24 ×
i.e = 12 × 3
∴ = 36
So B's 1 day work =
So, The (A + B) 's 1 day work = A's 1 day work + B's 1 day work
i.e = +
=
= =
i.e (A + B) together 1 day work =
∴ Work completed by (A + B) working together is in = 20 days
So, Time taken to complete 80% of the work = 80% × 20 days
= × 20 days
= 16 days
So, Time taken to complete 80% of the work when A and B works together = 16 days
Hence, Time taken to complete 80% of the work when A and B works together is 16 days Answer