Math, asked by poongavanamvishal, 11 months ago

a can do a work in 45 days he worked at it for 15 days and then B alone finish the remaining work in 24 days find the time taken to complete 80% of the work if they work together​

Answers

Answered by bhagyashreechowdhury
6

The time taken to complete 80% of the work if A & B work together is 16 days.

Step-by-step explanation:

A alone can do a work in 45 days

So, work done by A in 15 days = \frac{15}{45}  = \frac{1}{3}

Remaining fraction of work that is done by B alone = 1 - \frac{1}{3} = \frac{2}{3}in 24 days

The whole work will be done by B alone in = 24 × \frac{3}{2} = 36 days

Now,  

Work done by A in 1 day = \frac{1}{45}

Work done by B in 1 day =   \frac{1}{36}

Work done by A and B together in 1 day is given by,

=   \frac{1}{45} + \frac{1}{36}

=   \frac{5+4}{180}

=   \frac{9}{180}

=   \frac{1}{20}

If, 1 whole work is done by A and B together in 20 days

Then, 80% of the work will be done in = 20 * \frac{4}{5}  = 16 days

-------------------------------------------------------------------------------------

Also View:

A can do a piece of work in 80 days. He works at it for 10 days & then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work?

https://brainly.in/question/3605419

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work?

https://brainly.in/question/5332206

A can do a piece of work in 60 days.he works for 15 days and then b alone finishes the remaining work in 30 days. the two together can finish the work in?

https://brainly.in/question/5406689

Answered by sanjeevk28012
3

Time taken to complete 80% of the work when A and B works together is 16 days

Step-by-step explanation:

Given as :

A can do a work in 45 days

A's 1 day work = \dfrac{1}{45}

So, work done by A in 15 days = 15 × \dfrac{1}{45}

                                                   = \dfrac{1}{3}

Remaining work = 1 - \dfrac{1}{3}

i.e  Remaining work = \dfrac{3-1}{3}  = \dfrac{2}{3}

Now,  B alone finishes the remaining work in 24 days

So, Remaining Work done by B in  24 days = 24 × \dfrac{3}{2}

i.e                                                                     = 12 × 3

∴                                                                       = 36

So B's 1 day work  = \dfrac{1}{36}

So, The (A + B) 's 1 day work = A's 1 day work + B's 1 day work

i.e                                            = \dfrac{1}{45}  +  \dfrac{1}{36}

                                               = \dfrac{4+5}{180}

                                               = \dfrac{9}{180} = \dfrac{1}{20}

i.e (A + B)  together 1 day work  = \dfrac{1}{20}

∴  Work completed by (A + B)  working together is in = 20 days

So, Time taken to complete 80% of the work = 80% × 20 days

                                                                           = \dfrac{80}{100} × 20 days

                                                                           = 16 days

So,  Time taken to complete 80% of the work when A and B works together = 16 days

Hence, Time taken to complete 80% of the work when A and B works together is 16 days   Answer

Similar questions