a can do a work in 45 days he works at it for 15 days and then B alone finishes the remaining work in 24 days find the time taken to complete 80 percentage of the work if they work together
Answers
Answer:
1/15+1/24
for 15 and 24
lcm
is 120
1/15+1/24
is 8+5/120is
13/120 so ans is 120/13
Time taken to complete 80% of the work when A and B works together is 16 days
Step-by-step explanation:
Given as :
A can do a work in 45 days
A's 1 day work =
So, work done by A in 15 days = 15 ×
=
Remaining work = 1 -
i.e Remaining work = =
Now, B alone finishes the remaining work in 24 days
So, Remaining Work done by B in 24 days = 24 ×
i.e = 12 × 3
∴ = 36
So B's 1 day work =
So, The (A + B) 's 1 day work = A's 1 day work + B's 1 day work
i.e = +
=
= =
i.e (A + B) together 1 day work =
∴ Work completed by (A + B) working together is in = 20 days
So, Time taken to complete 80% of the work = 80% × 20 days
= × 20 days
= 16 days
So, Time taken to complete 80% of the work when A and B works together = 16 days
Hence, Time taken to complete 80% of the work when A and B works together is 16 days Answer