Math, asked by udaykumar965259, 10 months ago

a can do a work in 4days b in 5 days and c in 10 days find the time taken by a, b, &c to do the work togethar

Answers

Answered by harshit622
2

Answer:

Work done by A in 4 days = 1/4

Work done by B in 5 days = 1/5

Work done by C in 10 days = 1/10

Work done By (A+B+C) = 1/4 + 1/5 + 1/10

= 5+4+2/20 = 11/20

Time taken by (A+B+C) = 20/11

Please mark it as brainliest answer....