A can do a work in 6 days and B can in 9 days. How many days will both take together to complete the work.
Darkavenger17:
hey
Answers
Answered by
1
heya mate here is your answer
A's 6days work = 1
B's 9days work = 1
one day work of A = 1/6
one day work of B = 1/9
A and B together's one day work
= 1/6 + 1/9
= 9+6 /54
=15/54
number of days taken by A and B together to complete their work = 54/15
A's 6days work = 1
B's 9days work = 1
one day work of A = 1/6
one day work of B = 1/9
A and B together's one day work
= 1/6 + 1/9
= 9+6 /54
=15/54
number of days taken by A and B together to complete their work = 54/15