A can do a work in 6 hours B can do it 5 hours. A,B and C together can do a work in 2 hours are required find out how many hours are required to complete the work by C?

Answers

Answered by Anonymous
19

Work done by A + B + C = 2 hours

→ (A + B + C)'s one day = 1/2

→ 1/6 + 1/5 + 1/C = 1/2

 

→ 1/C = 1/2 - (1/6 + 1/5)

→ 1/C = 1/2 -(5 + 6)/30

→ 1/C = 1/2 - 11/30

→ 1/C = (15 - 11)/30

→ 1/C = 4/30

→ 4C = 30

→ C = 15/2

→ C = 7(1/2)

Hence, Work done by C = 7(1/2) hours