'A' can do a work in 8 days and 'B' in 12 days. If they work on it
together for 4 days, then what part of the work is left?
(A) 1/6
(B) 3/20
(C) 5/6
(D) 17/20
Answers
Answered by
0
Answer:
answer is a 1/6 mark me as brain list
Similar questions
Math,
3 months ago
India Languages,
3 months ago
History,
3 months ago
Social Sciences,
6 months ago