A can do a work in 8days and B can do the same work in 12 days. In how many days they will complete the work if they work together?
Answers
Answered by
1
Answer:
4.8 days
Step-by-step explanation:
1/8 + 1/12 = 20/96
so time taken by both = 96/20 = 4.8 days
Answered by
0
Answer:
Work done by a man in =8days
same work done by another man=12 days
time taken by them to complete the work together =
(8-4=12)