A can do a work in 8days and B can do the same work in 12 days. In how many days they will complete the work if they work together?​

Answers

Answered by classofankur
1

Answer:

4.8 days

Step-by-step explanation:

1/8 + 1/12 = 20/96

so time taken by both = 96/20 = 4.8 days

Answered by pradhansasmita67
0

Answer:

Work done by a man in =8days

same work done by another man=12 days

time taken by them to complete the work together =

(8-4=12)