A can do apeice of work in 4 days, B can do it in 6 days. How many days A and B take to complete working together.
Exam h serious answer dena
Answers
Answered by
23
A can do a peice of work in 4 days, B can do it in 6 days. How many days A and B take to complete working together.
✯
✏ Number of days required to do the work = 4 days.
✏ ∴ In 1 day, A can work = 1/4
✯
✏ Number of days required to do the work = 6 days.
✏ ∴ In 1 day, B can work = 1/6
✏ Total work done by A and B in 1 day = 1/4 + 1/6
=
=
=
✏ Number of days taken by A and B to complete the work together =
⠀⠀⠀⠀⠀⠀=
⠀⠀⠀⠀⠀⠀=
⠀⠀⠀⠀⠀⠀= 2
= 2 days.
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Answered by
1
Answer:
answer is
2 12/5......