a can do apiece of work in 12days and b alone xan do it in 16 days . they worked together on it for 3 days and then A left. hiw lond did b take to finish the renaining work
Answers
Answered by
2
Answer:
☆ A's 1 day's work=1/12
♧B's 1 day's work=1/16
♡(A+B)'s 1 day's work=1/12+1/16=4+3/48=7/48
♤(A+B)'s 1 day's work=7/48×3=7/16
◇Remaining work=1-7/16=16/16-7/14=9/16
♡Time taken by B to finish the remaining work=9/16×16=9
Ans; 9 days.