Math, asked by bhaveshkumar2627, 5 months ago

A can do as much work in 3 days as
C in 5 days. B can do as much work
in 3 days as C can do in 2 days.
What time would B require to do a
work if A takes 24 days to finish it?​

Answers

Answered by sumanthbhat99
3

Step-by-step explanation:

3A=5C 6A=10C

3B=2C 15B=10C

6A=15B

2A=5B

A finishes in 24 days =24A

24A=12×5B

=60B

B requires 60 days to do the work