A can do as much work in one day as B can do in 2 days or as C can do in 3
days or as D can do in 4 days. They together finish a piece of work in 8 days. How many
days would C take to do it alone?
Answers
Answered by
4
Answer:
Here's your answer》》》》》》》》
Step-by-step explanation:
A can do a work in a day
B can do a work in 2 days
C can do the same work in 3 days
Therefore let same work done by them on a day be X
A=x
B=x+2
C=x+3
ATQ.
x + x+2 + x+3 = 8
3x + 5 = 8
3x = 3
x = 1
Therefore C = x + 3
= 4 days
Hope it helps you.........