A can do of a piece of work in 14 days and with the help of B, he is able to finish the work in 6 days. Then find the time taken by B to finish the work​

Answers

Answered by sapnasharmadevansh
1

Answer:

12 days.

Step-by-step explanation:

Assuming that B alone takes x days to finish the work. Then A alone can finish it in (x−6) days

Now A’s one day’s work + B’s one day’s work =1/x + 1/x−6

and (A+B)’s one day’s work =1/4

1/x + 1/x−6 = 1/4

x-6+x/x(x-6) = 1/4 = 2x-6/x 2 -6x = 1/4 =

8x−24=x2−6x ⇒x2−14x+24=0

⇒x2−12x−2x+24 = 0

⇒(x−12) (x−2) = 0

⇒x=12 or x = 2 x cannot be less than 6.

So x=12 Therefore, B also can finish the work in 12 days.

hope this helps..