Math, asked by shwetagore, 1 month ago

A can do of the given work in 3 days and B can do of the same work in 4 days. 5 6 They work together for 2 days and B leaves. In how many days will A finish the remaining work?​

Answers

Answered by debbarmaninobi092
1

Step-by-step explanation:

Hello kya app rabindranath tagore ki poti hai ♥☺︎☺︎☺︎

heheheheh majak kar raha tha.

Answered by Alyshakashyap
0

Answer:

5 days or 4days