Math, asked by krishnashindev, 2 months ago

A can do peice of work in 25 days and B can finesh it in 20 days, both started together,after 5 days A left. In how many days will B finesh the remaining​

Answers

Answered by EliteZeal
107

A n s w e r

 \:\:

G i v e n

 \:\:

  • A can do piece of work in 25 days

  • B can finish it in 20 days

  • A & B worked together for 5 days after that A left

 \:\:

S o l u t i o n

 \:\:

 \underline{\bold{\texttt{One day work of A :}}}

 \:\:

A can finish the work in 25 days

 \:\:

 \sf \dfrac { 1 } { 25 }

 \:\:

 \underline{\bold{\texttt{One day work of B :}}}

 \:\:

B can finish the work in 20 days

 \:\:

 \sf \dfrac { 1 } { 20 }

 \:\:

 \underline{\bold{\texttt{One day work when A and B work together :}}}

 \:\:

 \sf \dfrac { 1 } { 25 } + \dfrac { 1 } { 20 }

 \:\:

 \sf \dfrac { 4 + 5 } { 100 }

 \:\:

 \sf \dfrac { 9 } { 100 }

 \:\:

 \underline{\bold{\texttt{5 days work when A and B work together :}}}

 \:\:

A & B worked together for 5 days

 \:\:

 \sf \dfrac { 9 } { 100 } \times 5

 \:\:

 \sf \dfrac { 9 } { 20 }

 \:\:

 \underline{\bold{\texttt{Remaining work after  initial 5 days :}}}

 \:\:

 \sf 1 - \dfrac { 9 } { 20 }

 \:\:

 \sf \dfrac { 11 } { 20 }

 \:\:

Given that remaining work is completed by B alone

 \:\:

  • Let B complete the remaining work in "x" days

 \:\:

So,

 \:\:

 \sf \dfrac { 1 } { 20 } \times x = \dfrac { 11 } { 20 }

 \:\:

➨ x = 11

 \:\:

  • Hence B will take 11 days to complete the remaining work alone

 \:\:

 \underline{\bold{\texttt{Total days required to complete the work :}}}

 \:\:

Number of days A & B worked together + Number of days B work alone

 \:\:

➜ 5 + 11

 \:\:

➨ 16

 \:\:

  • Hence total days required to complete the work is 16
Similar questions