A can do peice of work in 25 days and B can finesh it in 20 days, both started together,after 5 days A left. In how many days will B finesh the remaining
Answers
Answered by
107
A n s w e r
G i v e n
- A can do piece of work in 25 days
- B can finish it in 20 days
- A & B worked together for 5 days after that A left
S o l u t i o n
A can finish the work in 25 days
➜
B can finish the work in 20 days
➜
➜
➜
➜
A & B worked together for 5 days
➜
➜
➜
➜
Given that remaining work is completed by B alone
- Let B complete the remaining work in "x" days
So,
➜
➨ x = 11
- Hence B will take 11 days to complete the remaining work alone
Number of days A & B worked together + Number of days B work alone
➜ 5 + 11
➨ 16
- Hence total days required to complete the work is 16
Similar questions