Math, asked by aayushsharma08, 11 months ago

A can do piece a work in 10 days and B alone can do it in 15 days.B works at it for 5days and then leaves,then A alone can finish the remaining work in how many days?​

Answers

Answered by shreyansgarg2004
1

Answer: 6 days 16 hours

Step-by-step explanation:

If B can do complete the work in 15 days then in 5 days he will be able to complete 1/3 of work

Work left = 1 - 1/3

= 2/3

A can do work in 10 days the he will be able to do the remaining (2/3) work will be done in

(2/3) × 10

= 6 days and 16 hours

Similar questions